Skip to the template

Job hazard analysis: erecting and dismantling scaffolds

Build up and take down a scaffold in stages, with the right people and checks.

  • 5 steps
  • 5 PPE items
  • Editable in Reldro
A supervisor in a hard hat and high-visibility vest holding a tablet under a clear sky

The job hazard analysis

PPE required: Hard hat, Safety glasses, Gloves, Safety boots, Fall arrest harness

  1. 1. Plan and prepare the base

    What could go wrong

    Settling or tipping on soft, uneven ground

    How we control it

    Check the ground. Use base plates and sole boards. Follow the maker's or designer's plan.

  2. 2. Erect in stages

    What could go wrong

    Falls during assembly; dropped components

    How we control it

    Fit guardrails as early as you can. Use fall protection where the system calls for it. Pass components by hand or hoist, and don't throw them.

  3. 3. Tie in and brace

    What could go wrong

    Collapse from loose ties or missing braces

    How we control it

    Tie to the structure at the spacing in the plan. Don't remove ties early.

  4. 4. Check, tag, and hand over

    What could go wrong

    Using an unfinished scaffold

    How we control it

    Have a competent person inspect it. Tag it as ready, or not ready, at every access point.

  5. 5. Dismantle

    What could go wrong

    Falls and falling parts as the structure comes apart

    How we control it

    Work from the top down. Keep the area below barricaded. Remove ties only as the scaffold comes down past them.

  • Only trained people should erect, alter, or dismantle a scaffold.
  • In the US, OSHA requires guardrails on platforms more than 10 feet (3 m) above a lower level.

When to use it

Use it each time a scaffold goes up, changes, or comes down. A competent person should supervise.

Review it with the crew before the work starts, change anything that doesn't match how you'll do the job, and update it when the method, the equipment, or the site changes.

Use this JHA in Reldro

  • It arrives ready to edit, and your crew uses it on their phone, even without signal.
  • Failed items become corrective actions with an owner and a due date.
  • Every completed one is kept with the site, the date and who did it.